Wednesday, November 26, 2008

the heat is on

Monday, November 24, 2008

Things are starting to wind down.
trim around the staircases
a bit of plumbing to do yet
putting on the pulls for the cabinets

Thursday, November 20, 2008

still pluging away at the stairs
counter tops have all been fastened down and
tile back splash has been put in
exhaust pipes for the heating systems are
being put in

Tuesday, November 18, 2008

Getting ready to install the stairs
up she goes
hold it there
set in place

Monday, November 17, 2008

The snow has pretty well curtailed any other
work outside, not that there is much else to do.
The top of the windows have been completed
The furnaces and plumbing are
continuing along
landings for the stairs are being put in as
well as other touch ups being done

Tuesday, November 11, 2008

this is the work that was done on Monday
as well as laying of most of the sod
the last of the sod was layed today as well
as some inside work being completed

Friday, November 7, 2008

today was a day to do some cleanup tasks
get ready for the dedication on Saturday

Thursday, November 6, 2008

todays group was from WRPS
there was a lot of shoveling and moving
of the gravel today
today saw the porches and the sidewalk poured

Wednesday, November 5, 2008

Another nice fall day.
The sod was delivered today along
with the topsoil for the lawns
the ladies from Global Village were her today
to help with the landscaping
first job was taking down the scaffolding
it was a day of shovelling and
moving the ground

Tuesday, November 4, 2008

Another warm day to take advantage of some
outdoor work.
fixing some siding issues
installing bathroom hardware
cutting the holes for the heating system
\
laying down the floors
making the cuts for the stairs